However, the SFOE has delegated this task to the FPI, which is empowerde to issue building permits to third parties within the scope of the applicable regulations.

In principle, all construction activities that are carried out at a distance of less than ten meters from the pipeline or less than thirty meters from an auxiliary installation require a permit. This applies to both permanent and temporary construction projects, as well as to major alterations to existing structures, including new buildings, road maintenance, supply lines, marquees, events, etc. The building application must be submitted online here.